Thank you for your interest in the proposed zoning change from RE-24 to P-1 at 4455 E. Camelback Road. If approved, the new parking spaces would support already existing businesses to the east, referred to as "The Park Office Buildings". We have met with any members of the community who would like to meet with us as well as hosted a neighborhood meeting. We continue to listen to the comments from the surrounding residents and have made significant changes to the proposal based on that feedback. Please review the images, project facts and contact us if you have any additional comments.
Aerial Site Map
The businesses at “The Park” office complex to the east of this property have developed to the point that the City’s minimum parking requirements, which are satisfied entirely by on-site parking, no longer meet tenant demand. The property owner has acquired the subject property and is now seeking to expand parking designated for office users to the adjacent lot to allow for continued growth of their tenant businesses. NO NEW ACCESS is provided to Lafyette or Camelback. The new parking use would be accessible only through the Park property.
The rezoning to P-1 would provide for proximate parking to support the thriving adjacent businesses and create defined connections through the pedestrian spine.
Changes we made in response to feedback.
Parking field redesigned to preserve Mushroom in place
—
Former fountain will be redesigned as a decorative planter
—
Detached sidewalks added to Lafayette and Camelback frontages
—
Landscape setback along Lafayette increased from 8’6” to 20’ with a 5,000 square foot open space element
Open space amenities added surrounding it utilizing semi-circle and circular pedestrian access consistent with the architectural theming at bank property
—
Pavers added at main entrances;
similarly for pedestrian paths crossing vehicular paths
—
Landscape setback along Camelback increased from 10’ to average of 19’
—
Parking field will have a minimum of 25% shade
Lafayette frontage enhanced with additional landscaping
—
Parking field reduced to 130 (with only 124 being “new” due to spaces lost at access points)
—
Pedestrian pathways will provide minimum of 75% shade
—
19 trees onsite today, over 40 reflected in new plan
Original Site Plan
New Site Plan
Case No. Z112-26-6
Rumor
vs.
Reality
This site is a dedicated park.
1
This site is privately owned and has been since 1964. It was recently sold in 2025 to the owners of The Park Office Buildings to the East. The proposal would retain open space elements and amenities along the Lafayette frontage, and the Mushroom on the property as well as the former fountain will remain in place. The fountain is proposed to be repurposed as an architectural planter.
The site is historically protected.
2
The site was formerly a part of the bank property, and is now a separate + 1.5 acre parcel. According to the case records on file with the City, this portion of the property retained separate RE-24 zoning to serve as a buffer to what was residential property to the east of the property when the Bank was rezoned to C-1 in 1965. That eastern property was rezoned in the late 1970's to C-O.
Because the Bank is a commercial structure that is over 50 years old, it would be eligible for Historic Preservation review.
If the site is rezoned to P-1, it can be developed into something else under that zoning designation.
3
Rezoning the site to P-1 from RE-24 limits the development to 3 uses: Surface Parking Lot, Carports or Public Utility Building. The current RE-24 could allow for 15 different uses. P-1 Zoning Ordinance
The proposal will require general conformance to the site plan that reflects this- unlike the prior zoning cases for the Bank property which did not include a stipulation that the project conform to a site plan.
The proposal is not a “Trojan Horse” for a future development. The C-O property is effectively maxed out on lot coverage and this parking field will help to keep the property occupied and a popular location for local businesses to thrive. The current tenant mix is almost entirely made up of locally owned businesses with many of the owners and employees residing in close proximity to the Office complex. The property owner is local and has owned the building since the early 2010s.
If approved, the site could be developed into a multi-story parking garage.
4
P-1 designation does not permit multi-story or below-grade parking garages, and only surface parking would be permitted under the proposed zoning.
Additional parking will negatively impact the neighborhood.
5
We have been told by neighbors that they are currently experiencing commercial traffic and parking on their residential streets and have had near misses with vehicles and partially blocked driveways. Additional parking will prevent the need for anyone to park in the adjacent community. The case stipulations regarding conformance to a site plan will also ensure that there is no future access proposed onto Lafayette Boulevard from the new parking lot.
There is already more than enough parking on the site today.
6
The request is intended to provide additional parking for “The Park” – the existing office/restaurant development. The existing development has very high occupancy and parking demand has resulted in patrons, employees, and visitors parking on surrounding public streets within the neighborhood. The proposed development of a satellite parking lot is intended to help accommodate existing demand and reduce neighborhood parking impacts. The number of spaces proposed is a function of the design and not any pre-determined metric. The current complex is sufficiently parked from a City Code standpoint, but the situation is one that there is sustained demand that exceeds it and requires the heavy use of valet parking to manage.
“The Park Office Buildings” are underparked.
7
The existing development is not technically under-parked under the City’s Code. A prior shared-parking analysis associated with the outdoor dining use permit established a required parking amount, and the property currently has slightly more spaces than that requirement. The argument for additional parking is based on observed demand, and neighborhood impacts rather than a current zoning deficiency, and the desire from the property owner to create a more accommodating experience for visitors and to facilitate a safer parking field serving the office which provides for additional parking, EV spaces, as well as bike parking.
The bank parking lot could be used for overflow parking instead of creating a new parking lot.
8
The Bank property is separately owned and controlled by the Bank, and there is no shared parking agreement. The subject property was acquired specifically because it is adjacent to the existing development and could provide parking under the Applicant's ownership and control from within the Office parking field.
The parking lot could eventually receive direct vehicular access to Lafayette Boulevard or Camelback Road.
9
No new vehicular access is proposed from Lafayette or Camelback. The proposed parking lot would be accessed internally through the existing development. A stipulation requiring general conformance to a site plan with specific regard to the lack of new driveway access onto Lafayette and Camelback
This new development will cause the “architectural mushrooms” to be displaced.
10
We have been able to keep the “architectural mushrooms” in their original locations due to our updated site plan.
You are removing the existing trees and not replacing them with as many new trees.
11
We acknowledge the importance of the landscaped environment and we are proposing a design that would replace the existing vegetation with new landscaping and additional trees- which will be almost double the amount of trees onsite today. New shading requirements by stipulation will also ensure that the shading is maintained in the future to provide for heat mitigation and also water conservation with the use of native, drought-tolerant species.
Next Steps \ Anticipated Schedule
If this proposal is approved site plan and permitting typically takes 9-12 months. Construction to follow.